Cost of topping up soil - per lorry/truck

Post by arjay » September 28, 2018, 10:07 pm

In the context of topping up soil on a building plot, does anyone know how much soil a typical lorry holds (in cubic metres), and what the current cost per lorry is?

I know how many cubic metres of solid, but want to work out how many truck loads that would involve and the cost.

User avatar
BillaRickaDickay
udonmap.com
Posts: 212
Joined: October 28, 2010, 6:32 pm

Re: Cost of topping up soil - per lorry/truck

Post by BillaRickaDickay » September 29, 2018, 3:14 am

This link may help:-

https://www.thaivisa.com/forum/topic/63 ... rks-isaan/

6 Wheel standard truck carries 6 cube, I recently paid 300bht a load which was sourced locally in Kut Chap
He's got his little y-fronts and he's got his little vest, Chaz Jankel, 1998. Mash it up Harry.

harry68
udonmap.com
Posts: 328
Joined: June 3, 2012, 7:37 am

Re: Cost of topping up soil - per lorry/truck

Post by harry68 » September 29, 2018, 4:03 am

Im out in Ban Dung and we pay 550 for 10 wheel average about 10 to 12 m3

User avatar
maaka
udonmap.com
Posts: 2825
Joined: October 9, 2007, 6:03 am

Re: Cost of topping up soil - per lorry/truck

Post by maaka » September 29, 2018, 3:50 pm

300bt for an old beaten up grey tip truck load

User avatar
Bandung_Dero
udonmap.com
Posts: 2472
Joined: July 10, 2005, 8:53 am
Location: Ban Dung or Perth W.A.

Re: Cost of topping up soil - per lorry/truck

Post by Bandung_Dero » September 29, 2018, 4:33 pm

Average around here is currently about 500 Baht (about 14 cubic metres or 16 tonne) - depending on how far they are traveling from the fish pond/pit they are digging. It's locally called 'Hin' (red/brown colored gravel) and the price includes a tractor for leveling.
Sent from my 1977 Apple II using 2 Heinz bake bean cans and piano wire!

User avatar
arjay
udonmap.com
Posts: 8352
Joined: October 2, 2005, 12:19 pm
Location: Gone to get a life, "troll free"

Re: Cost of topping up soil - per lorry/truck

Post by arjay » October 2, 2018, 1:56 am

Thanks all for your input. I've passed it onto the wife.

Would I be right to assume that any new topping up, will likely settle by about 20% over the first year or so, depending on how much it is compacted when originally topped up?

User avatar
maaka
udonmap.com
Posts: 2825
Joined: October 9, 2007, 6:03 am

Re: Cost of topping up soil - per lorry/truck

Post by maaka » October 2, 2018, 5:30 am

now dont quote me on this, but I read somewhere that if your filling in a rice field with truck loads of dirt you shouldnt build on it for two years, so as it has time to settle..Now to counter that, my builder is dumping 12 truck loads on my place and going to build a workshop /bungalow on top without delay..He said it was ok, because hard ground underneath and we only putting a foot over the top and filling in low spots I cant really see...so there you go..I woukld expect some settling , but as to percentage havent a clue

harry68
udonmap.com
Posts: 328
Joined: June 3, 2012, 7:37 am

Re: Cost of topping up soil - per lorry/truck

Post by harry68 » October 2, 2018, 5:33 am

will settle more than 20% i would go for minimum 30%
this wet season i lost 30% of the 2 rai i topped up 1.2 metres

User avatar
sometimewoodworker
udonmap.com
Posts: 1252
Joined: October 7, 2008, 11:19 am

Re: Cost of topping up soil - per lorry/truck

Post by sometimewoodworker » October 2, 2018, 7:53 am

maaka wrote:
October 2, 2018, 5:30 am
now dont quote me on this, but I read somewhere that if your filling in a rice field with truck loads of dirt you shouldnt build on it for two years, so as it has time to settle..Now to counter that, my builder is dumping 12 truck loads on my place and going to build a workshop /bungalow on top without delay..He said it was ok, because hard ground underneath and we only putting a foot over the top and filling in low spots I cant really see...so there you go..I woukld expect some settling , but as to percentage havent a clue
If there's going to be a problem with the workshop/bungalow will depend on exactly how he builds, there will be around 20% air in the fill so any thing that requires long term support from the fill is likely to fail as the fill compacts, conversely if the fill is just acting as a support for the concrete while it cures and isn't really needed after then there is no problem.
Jerome and Nui's new househttp://bit.ly/NJnewHouse

User avatar
sometimewoodworker
udonmap.com
Posts: 1252
Joined: October 7, 2008, 11:19 am

Re: Cost of topping up soil - per lorry/truck

Post by sometimewoodworker » October 2, 2018, 7:59 am

arjay wrote:
October 2, 2018, 1:56 am
Thanks all for your input. I've passed it onto the wife.

Would I be right to assume that any new topping up, will likely settle by about 20% over the first year or so, depending on how much it is compacted when originally topped up?
The compaction that fill usually gets makes little difference unless you are using things like these to compact
IMG_5119.JPG
IMG_5119.JPG (24.32 KiB) Viewed 936 times
Mostly a tractor is used and they are designed to not compact the soil.
Jerome and Nui's new househttp://bit.ly/NJnewHouse

User avatar
vincemunday
udonmap.com
Posts: 1979
Joined: December 11, 2014, 11:36 pm
Location: Udon Thani ex North Stifford and Ramsgate
Contact:

Re: Cost of topping up soil - per lorry/truck

Post by vincemunday » October 2, 2018, 9:21 am

Some of the settlement will depend on the type of soil that's delivered, when we topped up the land in town we had nice brown soil that settled quite a lot but when we topped up our land in Ban Tad they delivered a red very cloying clay like soil that hardly settled at all. In the first instance we waited a couple of years before we built and the second we waited just a year and the builders moaned like crazy that it was like digging concrete.
"I don't risk my life for the sake of my children, I risk it for the sake of everyone's children" Stephen Yaxley-Lennon aka Tommy Robison - Free speech activist 2017

pipoz4444
udonmap.com
Posts: 490
Joined: April 8, 2011, 1:33 am
Location: All Over the Place

Re: Cost of topping up soil - per lorry/truck

Post by pipoz4444 » October 2, 2018, 11:01 pm

Bought 1 Rai of land in middle of 2012, cleared it and then put 500 mm fill (relatively dry red clay fill) over the whole area some 3 months later. Only spread it with a Tractor blade an over the next 20 months, it settled about 120 mm

Middle of 2014, (20 months after placing the fill), I started to build on it. It was hard as a rock, so much so, that when digging the pad footings they would dig the first 300 mm, then fill the hole with water, then dig another 300 mm and so on. It was hard 300 mm into that fill layer.

Underneath the fill was virgin clay (never a rice paddy) so this too was hard to dig into.

This was only an original 500 mm thick fill layer. It may be a different story if you dump a 1.0 meter thick fill layer.

bluejets
udonmap.com
Posts: 790
Joined: March 17, 2008, 10:05 am
Location: Australia

Re: Cost of topping up soil - per lorry/truck

Post by bluejets » October 3, 2018, 6:29 am

maaka wrote:
October 2, 2018, 5:30 am
now dont quote me on this, but I read somewhere that if your filling in a rice field with truck loads of dirt you shouldnt build on it for two years, so as it has time to settle..Now to counter that, my builder is dumping 12 truck loads on my place and going to build a workshop /bungalow on top without delay..He said it was ok, because hard ground underneath and we only putting a foot over the top and filling in low spots I cant really see...so there you go..I woukld expect some settling , but as to percentage havent a clue
In Aus going back a while ('86) it used to be that one could not build on filled or reclaimed land for 20 years.
They seem to have relaxed that for domestic.
Commercial still tend to bring in the massive spiked roller vibrator units.
Housing they tend to use cracker dust and I've seen the trend can be a build-up of around 500-600mm above the natural soil and there is no waiting, just run over with the hand machine vibrator units.
Seems to extend maybe 1 metre past the extremities of the slab.
Then again in Aus for domestic they largely use raft slabs.
Soil ( if you can call it that) at my place is the same as in most parts of Thailand, crappy clay and I remember putting 20mm steel deformed reo bars in my raft slab back in "86.
Also remember the builder saying how much clay moves, expands and contracts also between wet and dry. I see it here, especially now in the drought here with large cracks appearing everywhere.
Hard to believe 5 years ago we had flood water up to the bottom of the windows.
Our land in Thailand we put 300 truck loads in 2 years ago, levelled off with the tractor and now has more ups and downs than a theme park ride.

User avatar
kopkei
udonmap.com
Posts: 1308
Joined: August 27, 2010, 6:55 am

Re: Cost of topping up soil - per lorry/truck

Post by kopkei » October 3, 2018, 8:42 am

these prices will vary depending area ,where the soil is coming from , how many you need....
cheapest din daeng , the sticky red clay ground they always use to start the fill ,best topped off with 20cm of hin daeng ,which contains more gravel stone making it very compact and non sticky when driven over , mostly they will give prices including clearing with the normal tractor (?) , when u can build on this is depending how much you have filled up and building style , mostly when need to put your footing in the new soil best to wait 1 year ...(footings are mostly 1m deep)
the din/hin daeng compact very quickly after 1 rain season ...
if you live baan noak (inland) it will be a lot cheaper than near a big city (muang)...
only one more advice , do not make it more complicated than it really is , i all ready get some headache of some postings here , and not forget TIT , do not compare with abroad ...good luck to all... ;)

User avatar
arjay
udonmap.com
Posts: 8352
Joined: October 2, 2005, 12:19 pm
Location: Gone to get a life, "troll free"

Re: Cost of topping up soil - per lorry/truck

Post by arjay » October 3, 2018, 7:41 pm

Thanks for the input everyone.

Essentially this land will be topped and levelled out and then left for a year or two before any building will take place.

It is a middle plot of three, on a sloping (to the side) site. The upper/higher left hand plot was topped up by 500mm (before settling) and then built on. So my wife is thinking of topping her middle plot up by a max of 1.5 metres, tapering between 0.5m on the uphill side to a max of 1.5m on the downhill side, and then leave that to settle.